I-20 at County Road (CR) 249/Old Mill Road
PROJECT WEBSITE: https://us278andoldmillroad-gdot.hub.arcgis.com/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/15/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Description:
The Georgia Department of Transportation (Georgia DOT) proposes to construct a new interchange along Interstate 20 (I-20) at Old Mill Road in Morgan County, Georgia. Old Mill Road in the vicinity of the new interchange would be widened from a 2-lane road to a 4-lane section with 20-foot raised median and rural shoulders and realigned to the west of its current location. The project would begin approximately 0.38 mile south of I-20 on Old Mill Road, construct a new bridge over I-20 to the west of the existing bridge, and terminate approximately 0.27 mile north of I-20 at a signalized intersection with a newly constructed Frontage Road (constructed under Georgia DOT PI No. 0018363, which would be let to construction in August 2022). Roundabouts would be constructed on Old Mill Road at the new I-20 ramp terminals. The existing Old Mill Road bridge over I-20 would be deconstructed and a new cul-de-sac would be constructed at the existing Old Mill Road just north of I-20 to provide local access to property owners. The proposed project length is approximately 0.73 miles.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|