I-285/I-20 West Interchange Reconstruction
PROJECT WEBSITE: https://majormobilityga.com/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/17/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The proposed Interstate (I) 285 and I-20 West Interchange project proposes for improvements of the interchange and addition of lanes along I-20. The proposed project includes reconstructing the interchange to remove left hand exits and improve design speed, and modification and/or replacement of existing bridges and ramps. An I-20 westbound collector-distributor (CD) system would be constructed from the Interchange to Fulton Industrial Boulevard. Construction of lanes and improvements would occur along the approximately 6.5 mile I-20 corridor in both directions between Thornton Road and Hamilton E. Holmes Drive and along approximately 2.4 miles of I-285 between D.L. Hollowell Parkway and Martin Luther King Jr. Drive. The project also includes the modification and/or replacement of bridges along I-20, including bridges over the CSX Railroad and the Chattahoochee River.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|