I-405, SR 522 Vicinity to SR 527 Express Toll Lanes Improvement Project

PROJECT WEBSITE: I-405 - SR 522 to SR 527 Capacity Improvements Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/04/2022

12 out of 12

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

No icon

Washington

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of Homeland Security

Department of Homeland Security, US Coast Guard

Description:

This project proposes to: 
• Create a dual express toll lane system on I-405 between the vicinity of SR 522 and SR 527 by adding one express toll lane in each direction.
• Widen 1-405 through the SR 522 interchange and build direct access ramps to the express toll lanes at SR 522.
• Build a partial direct access ramp at SR 527 (to the east, north, and south) to provide connections to the Canyon Park Park-and-Ride.
• Construct other associated improvements including local roadways, noise walls, stormwater facilities, and fish passage improvements.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete