I-495 Southside Express Lanes

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/15/2030

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

The Virginia Department of Transportation (VDOT) is studying potential impacts of its Proposed Action to extend the existing Express Lanes (High Occupancy Toll [HOT]) along a section of the I-95/I-495 (Capital Beltway) from the I-95/I-395/I-495 interchange in Fairfax County, Virginia by approximately 11 miles to MD 210 in Prince George’s County, Maryland (hereafter, “study limits”). It is anticipated that the Proposed Action would be implemented largely within the Capital Beltway’s existing right of way. No widening of the Woodrow Wilson Memorial Bridge is anticipated. While the I-95/I-395/I-495 and MD 210 interchanges provide logical termini for the study, it is assumed that improvements could extend beyond these points to ensure proper connections to the system, except at localized areas where ramp access points may be considered.
 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete