I-5 Freight Corridor

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/30/2019

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

California

California

Description:

The California Department of Transportation (Caltrans) proposes a project to upgrade 10 bridges along the Interstate 5 (1-5) corridor from the Los Angeles River Bridge and Separation [post mile (PM) 27.07] to the Templin Highway Bridge (PM 67.0), 64.3 kilometers (km) (39.93 miles) (mi) across the San Fernando Valley and Santa Clarita Valley, ending within the Tehachapi Mountains at Templin Highway at the northern terminus. The project proposes to improve freight efficiency along 1-5 from State Route (SR) 134 to the Templin Highway Bridge in Los Angeles County by providing standard vertical clearance of 16 feet (ft)-6 inches (in), eliminating load capacity restrictions for heavy loads, and reducing the frequency of route closures due to maintenance.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete