USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

I-580 Bridge Rehabilitation Project

PROJECT WEBSITE: https://d4vpm3.wixsite.com/i-580-bridge-rehab

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/15/2022

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Description:

The California Department of Transportation (Caltrans) proposes to upgrade existing non-standard bridge barrier railings to current on the following three bridges located along Interstate 580 (I-580) in the City of Oakland in Alameda County: the Fruitvale Avenue Undercrossing [UC] (Bridge Number 33-0324) at postmile (PM) R41.43, the Broadway-Richmond Boulevard UC (Bridge Number 33- 0285) at PM 44.51, and the Webster Street UC (Bridge Number 33-0296) at PM 44.81. Caltrans also proposes to seismically retrofit the Fruitvale Avenue UC and the Broadway-Richmond Boulevard UC. Additionally, Caltrans proposes to demolish two pedestrian overcrossings (POC) spanning I-580 and either construct a new replacement POC over I-580 connecting Crescent Street to MacArthur Boulevard or instead enhance the nearby Grand Avenue, MacArthur Boulevard, and Santa Clara Avenue between the touchdowns of the existing POCs. The POCs proposed to be demolished are: the Santa Clara Avenue POC (Bridge Number 33-0312) at PM 43.76 and the Van Buren Avenue POC (Bridge Number 33-0313) at PM 43.75. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete