I-69 Evansville, IN - Henderson, KY
PROJECT WEBSITE: I-69 OHIO RIVER CROSSING
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/15/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of War, US Army Corps of Engineers - Regulatory
Department of Homeland Security, US Coast Guard
Department of the Interior, Fish and Wildlife Service
Indiana
Description:
This was originally a KY lead project named Future I-69 Bridge over the Ohio River Between Henderson and Evansville near US-41 Bridges (2-1088).
Purpose of the project will be to develop a financially feasible solution to the project’s identified needs. At this time, the anticipated primary purpose of this project will be to:
• Provide cross-river system linkage and connectivity between I-69 in Indiana and I-69 in Kentucky that is compatible
with the National I-69 Corridor.
• Develop a solution to address long-term cross-river mobility.
• Provide a cross-river connection that reduces traffic congestion and delay.
• Improve safety for cross-river traffic.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|