IH 35 (US 77 - Lone Oak Rd.)
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/07/2019
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
Proposing to widen and reconstruct Interstate Highway 35 (IH 35) from four to six main lanes in Denton and Cooke counties, Texas, from United States Highway (US) 380 (University Drive West) to approximately 0.7 mile north of Farm to Market Road (FM) 3002 (Lone Oak Road). The proposed improvements would begin north of the IH 35 east/west split in the city of Denton and extend north along IH 35 through the city of Sanger to north of FM 3002 in Cooke County, for a total distance of approximately 15.2 miles (see Figure 1 in Appendix A). The proposed action would construct three main lanes in each direction and two frontage road lanes in each direction along this section of IH 35. Auxiliary lanes would be constructed in certain places between ramp entrances and exits. The existing interchanges would be reconstructed and the existing two-way frontage roads would be converted to one-way operation. The improvements that are proposed at the cross streets would accommodate one-way frontage road operations and turnarounds.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|