IMPROVEMENTS TO SR-1/MANOR DR. OVERCROSSING

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/30/2026

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Description:

The California Department of Transportation (Caltrans), in cooperation with the City of Pacifica (City), and the San Mateo County Transportation Authority (SMCTA), proposes to modify the State Route (SR) 1/Manor Drive overcrossing. The SR 1/Manor Drive Overcrossing Improvement Project (project) extends for approximately 0.7 mile along SR 1, from post mile (PM) R44.77 to R45.48. It includes portions of Manor Drive, Palmetto Avenue, Oceana Boulevard, and Milagra Drive in Pacifica and San Mateo County. The project would widen or replace the Manor Drive overcrossing between Palmetto Avenue and Oceana Boulevard, replace the existing all-way-stop-controlled intersections with traffic signals, and construct new sidewalks and bicycle lanes. The project may include the construction of a new northbound SR 1 freeway on-ramp at Milagra Drive and Oceana Boulevard. Conceptual plans are included in Attachment B. The project proposes to address existing and future congestion, gaps in the sidewalk and bicycle lane network, and roadway and structure deficiencies that reduce safety for motorists, pedestrians, and cyclists in the Manor Drive overcrossing area. Caltrans, as assigned by the Federal Highway Administration (FHWA), is the lead agency under the National Environmental Policy Act (NEPA). Caltrans is the lead agency under the California Environmental Quality Act (CEQA). 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete