Interstate 10/Koli Road Traffic Interchange
PROJECT WEBSITE: https://azdot.gov/koliroad
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/15/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Arizona
Description:
The Arizona Department of Transportation (ADOT), as the lead agency and project sponsor, in collaboration with the Gila River Indian Community (Community), the Bureau of Indian Affairs (BIA), the Federal Highway Administration (FHWA) and the Maricopa Association of Governments, has initiated a Design Concept Report (DCR) and an environmental study (assumed to be an Environmental Assessment or EA) for the proposed Interstate 10/Koli Road Traffic Interchange.
The proposed I-10/Koli Road Traffic Interchange would be located on I-10 between the existing Wild Horse Pass Boulevard and State Route 347/Queen Creek Road traffic interchanges.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|