Interstate 5 Managed Lanes Project - Orange County

PROJECT WEBSITE: Interstate 5 Managed Lanes Project - Los Angeles

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/01/2025

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects
Major Infrastructure Projects

Caltrans

LEAD AGENCY
California, CalTrans

Description:

The I-5 Managed Lanes Project includes a 15-mile section between Red Hill Avenue, south of SR-55, and the Orange/Los Angeles County Line that will address operational deficiencies related to HOV degradation through studies of alternatives that include priced managed lanes (also known as Express Lanes) strategies. The purpose of this project is to improve the overall movement of people and goods along this section of I-5 through the cities of Tustin, Santa Ana, Orange, Anaheim, Fullerton, Buena Park and La Mirada. Currently, the project corridor has three major freeway-to-freeway interchanges at SR-55, SR-22/SR-57 and SR-91 and at least one HOV lane in each direction.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete