Interstate 680 Express Lanes from State Route 84 to Alcosta Boulevard Project
PROJECT WEBSITE: https://www.alamedactc.org/wp-content/uploads/2019/01/1490000_I680_EL_SR84-Alco…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/04/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The California Department of Transportation (Caltrans), in cooperation with the Alameda County Transportation Commission (Alameda CTC), proposes to construct High Occupancy Vehicle/express lanes (HOV/express lanes) on northbound and southbound Interstate 680 (I-680) from State Route (SR) 84 (Vallecitos Road) in Alameda County to north of Alcosta Boulevard in Contra Costa County. HOV/express lanes are specially designated freeway lanes that are free for eligible HOVs and also give other vehicles, including single-occupant vehicles (SOVs), the option to pay a toll to use the lane.
The proposed project extends for approximately 9 miles along I-680 from post mile (PM) R10.6 to R21.9 in Alameda County and from PM R0.0 to R1.1 in Contra Costa County. The new HOV/express lanes would pass in or near the cities of Pleasanton, Dublin, and San Ramon, and the community of Sunol.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|