Lake Elmo Airport Development Project, Environmental Assessment
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/31/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
1.Relocate Runway 14/32 to the northeast and extend to the southeast,
including all necessary grading, clearing, and runway lighting.
2. Construct cross-field taxiway to serve new Runway 14 end.
3. Convert existing Runway 14/32 to a partial parallel taxiway and construct other
taxiways as needed to support the relocated runway, including taxiway lighting and/or reflectors
4. Extend Runway 04/22 to the northeast and add necessary lighting and taxiway
connectors.
5. Realign 30th Street North around the new Runway 14/32 runway protection
zone to reconnect with Neal Avenue North.
6. Construct a connector road.
7. Establish non-precision instrument approach procedures to all four runway
ends.
8. Remove approximately 20 acres of trees.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|