Lincoln South Beltway (1306-EA)

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/27/2018

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The proposed Lincoln South Beltway project would construct a new 11-mile east-west freeway south of the City of Lincoln, located between US-77 on the west and N-2 on the east, and generally located 0.5 miles south of Saltillo Road.  The new Freeway would include the following elements:  four travel lanes (two in each direction), inside and outside shoulders, a depressed median, and five grade-separated interchanges, including freeway connections with US-77 and N-2 and local road connections at S. 27th Street, and S. 68th Street, and S. 82nd Street. 

The purpose of the Lincoln South Beltway is to improve east-west connectivity for regional and interstates travel through Nebraska and to reduce conflicts between local and through traffic, including heavy through traffic, in Lincoln.  The project is needed to address increased travel demand on Lincoln's transportation network, conflicts between local and regional trips along Nebraska Highway through Lincoln, and challenges associated with heavy truck traffic through Lincoln.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete