Little Cottonwood Canyon EIS

PROJECT WEBSITE: Little Cottonwood Canyon EIS Website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/29/2023

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Utah

LEAD AGENCY
Utah

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Utah Department of Transportation (UDOT) has prepared an Environmental Impact Statement (EIS) to evaluate transportation solutions to substantially improve roadway safety, reliability, and mobility on State Route 210 (S.R. 210) from Fort Union Boulevard through the Town of Alta for all users on S.R. 210.

UDOT has selected Gondola Alternative B as the selected primary alternative (which includes tolling as a travel demand management strategy) with phased implementation of components of the Enhanced Bus Service Alternative. Gondola Alternative B includes a gondola alignment from a proposed development south of North Little Cottonwood Road and east of the La Caille restaurant to both the Snowbird and Alta ski resorts in Salt Lake County, Utah. The Gondola Alternative B includes a 2,500-space parking structure at the base station, a new base station access road, and roadway improvements to SR-210. UDOT will implement the following components of the Enhanced Bus Service Alternative: Improved and Increased Bus Service, Resort Bus Stops and a Bus Maintenance and Storage Facility.

UDOT has selected the following sub-alternatives as supporting elements: the Five-lane Alternative on Wasatch Boulevard Alternative; Snow Sheds with Realigned Road Alternative; Trailhead Improvements and No Roadside Parking within ¼ mile of Trailheads Alternative; No Winter Parking Alternative; and the Gravel Pit Mobility Hub.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete