USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Livingston Avenue Bridge Replacement Project

PROJECT WEBSITE: https://www.dot.ny.gov/livingstonavebridge/environmental

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/31/2022

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Railroad Administration

Description:

The Livingston Avenue Bridge (Bridge Identification Number [BIN] 7092890) is a rail bridge crossing the Hudson River between Rensselaer and Albany, New York. The bridge is located at Milepost QC 143.1 on the CSX Transportation, Inc. (CSX) Subdivision of the Empire Corridor, which is the principal passenger and freight route in New York State. The United States Department of Transportation (USDOT) designated the Empire Corridor as a High Speed Intercity Passenger Rail (HSIPR) corridor in 1998, based on its utility and its potential for future development. The 463-mile Empire Corridor traverses 24 counties between New York City and Niagara Falls and transports both freight and passengers.

The National Railroad Passenger Corporation (Amtrak) uses the existing bridge for passenger rail service. Trains use the bridge to serve areas north or west of Albany, including Amtrak’s Ethan Allen Express route to Rutland, Vermont, Amtrak’s Adirondack route to Montreal, Canada, and service to Niagara Falls, Chicago, and Toronto. CSX and Canadian Pacific Railway (CP) occasionally run freight trains across the bridge.

The New York State Department of Transportation (NYSDOT) identified two feasible Build Alternatives. Both would construct a new bridge—including a lift navigation span and through-truss and girder approach spans—adjacent to the existing bridge. Both alternatives would also involve rehabilitation and reconfiguration of the Hudson Line rail bridges over Water and Centre Streets in Albany. For both replacement alternatives, the new bridge would consist of a vertical lift span with through-truss and girder approach spans. The lift span would be located east of the existing swing span within the channel maintained by the U.S. Army Corps of Engineers (USACE) and would be somewhat more centered within the USACE channel, which is approximately 600 feet wide at the bridge. Both Build Alternatives would also include a shared use path for pedestrian and bicycle access across the Hudson River. The two Build Alternatives are:

  • Northern adjacent alignment
    • new alignment would be skewed relative to the alignment of the existing bridge because of the needed geometry for connections on the west side of the river  
  • Southern adjacent alignment 
    • new alignment would be parallel and south of the existing bridge

During construction, the new bridge would be constructed span-by-span to allow the existing swing span to remain in operation until the new lift span is operational. The float-in of the final new span adjacent to the existing swing span and float-out of the existing span(s) would take place during a closure to both rail and marine traffic. Once the new bridge is complete and in operation, the old bridge would be removed.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete