Maryland Parkway High Capacity Transit

PROJECT WEBSITE: Maryland Parkway High Capacity Transit

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/16/2019

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

Maryland Parkway High Capacity Transit corridor is an 8.7‐milelong project that will replace the existing local Route 109 service with an enhanced transit system that will provide speed and service quality improvements within the corridor and significantly increase transit ridership.

The project alignment extends from the Las Vegas Medical District through Downtown Las Vegas and the Bonneville Transit Center, along Maryland Parkway to Sunrise Hospital, The Boulevard Mall, the University of Nevada Las Vegas (UNLV), to McCarran International Airport.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete