USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Meadow Farms ADA Improvements

PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-9/district-9-current-projects/mead…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/10/2020

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

California

California

Description:

Caltrans proposes to construct new sidewalks, curbs and gutters, driveways, and ramps on both sides of US 395 between N. See Vee Ln and N. Barlow Ln. This work may be constructed in one phase or possibly split into two phases consisting of a north and a south build.

Drainage work would be needed to accommodate the new concentrated flows from the new curb/gutter work. Existing drainage inlets and culverts may need to be relocated or upgraded to accommodate these increased flows. New drainage inlets and culverts may also be necessary, Oil water separator(s) would likely be needed to treat storm water run over before being discharged to the creek. The existing ditch on the north side of the highway, between N. Barlow Ln to N. See Vee Ln would likely need to be relocated at various locations, the amount dependent on the alternative chosen.

 

Need: This segment of US 395 within Inyo County services some of the highest density residential areas in Inyo County. Consequently this area has some the highest rates of pedestrian, bicycle, and automobile use. Lack of standard shoulders for this facility, no continuous sidewalks or bike lanes, and lack of defining access control features creates conflicts between these users.

 

Purpose: To improve the safety of this segment of US 395 by installing ADA compliant pedestrian facilities and road side features to reduce conflicts between pedestrians, bicyclists, and automobiles within the project limits and increase intermodal use. Installation of ADA accessible features will allow a broader range of pedestrian use and connectivity with the community. Installation of roadside features such as curb and gutter along with dedicated driveways

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete