Merced Seismic Restoration

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/07/2022

7 out of 7

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

No icon

States

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

California

California

Description:

The California Department of Transportation (Caltrans) proposes to seismically retrofit seven bridges in Merced County to increase their structural integrity in case of a seismic event and upgrade deficient bridge railings to current standards.

The project would seismically retrofit seven bridges on State Routes 59, 140, and 152in Merced County to increase their structural integrity by doing the following:

  • Adding steel column casings
  • Retrofitting hinges with pipe seat extenders and cable restrainers

The work would bring the bridges up to current standards and minimize the risk of collapse during a seismic event. The project would also upgrade the non-standard bridge railings. In addition, 8-foot shoulders would be added on the Los Banos Creek/West Branch Mud Slough bridge (Bridge Number 039-0090); the bridge currently has no shoulders and does not match the approaching oadway, which has 8-foot shoulders.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete