Mississippi River Bridge South GBR: LA 1 LA 30 Connector

PROJECT WEBSITE: https://www.mrbsouth.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/28/2026

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The proposed project includes a new bridge across the Mississippi River to connect LA 1 on the west bank to LA 30 on the east bank. The proposed project is being developed with a preliminary purpose: To provide increased capacity and improved connectivity across the MS River, and to provide an alternate route for emergency evacuations in response to incident-related closures. The new bridge is expected to be a tolled facility. In times of emergency evacuation, DOTD will suggest that the concessionaire suspend the toll. The estimated project cost is $1.5 Billion. This project will require a Section 404 permit from the Corps of Engineers, a Water Quality Certification from LADEQ, and a U.S. Coast Guard bridge permit. The approximate location of the bridge is 30°16'47.0"N 91°12'04.1"W

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete