Monterey Bay Sanctuary Scenic Trail

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/08/2021

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The North Coast Rail Trail Project is a 7.5-mile multi-use bicycle and pedestrian trail proposed to extend along the railroad corridor from Wilder Ranch State Park in the south to Davenport in the north in unincorporated Santa Cruz County. The project also includes improvements to three existing parking areas (Davenport Beach, Bonny Doon Beach, and Panther/Yellowbank Beach) as well as a new crossing of Highway 1 in Davenport. The project has two segments, the 5.4-mile section from Wilder Ranch to Panther/Yellowbank Beach is currently funded. Construction funding is yet to be secured for the remaining 2.1 miles to Davenport, CA.  The environmental compliance encompasses both segments of the proposed trail. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete