USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Montgomery Intermodal Container Transfer Facility

PROJECT WEBSITE: Montgomery Intermodal Container Transfer Facility Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/08/2024

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Railroad Administration

Description:

The proposed project consists of the construction of an Intermodal Container Transfer Facility (ICTF) on an approximately 272-acre property owned by the ASPA in Montgomery, Alabama. The facility will consist of two 3,500 linear feet process rail tracks, one 3,500 linear foot support rail track, a maintenance building, and an administration building. Container stacking areas will be provided adjacent to the process tracks. Rubber tired gantry cranes will be employed to load and unload trains and trucks at the facility. Ten thousand (10,000) linear feet of lead track will also be constructed parallel to the existing CSXT main line to provide rail access into the ICTF. Truck access into the facility will be provided through intersection improvements within the Alabama Department of Transportation (ALDOT) right of way (ROW) at U.S. Highway 31 (US 31) and Green Leaf Drive.  Once operational, the Montgomery ICTF is anticipated to be open from 6:00 a.m. to 6:00 p.m. Monday through Friday.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete