Morristown Airport: Construct Hangars, Apron, Terminal Building, Shift Taxiway Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/03/2023

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

- Construction of an approximately 5,500-square foot (SF) terminal/FBO building
- Construction of two, 27,000+/- SF corporate hangars
- Construction of automobile access and approximately 59 automobile parking spaces to serve the terminal/FBO building and hangars. Would require the relocation of the existing fence and fuel truck gates.
- Remarking/repurposing of the existing apron to accommodate parking spaces for 27 Airplane Design Group (ADG) I based aircraft, and ADG III movement areas
- Relocation of the existing Taxiway 'K' to connect to Taxiway 'B' to accommodate taxilane objectfree area (TLOFA) dimensions for ADG III aircraft
- Construction of a new apron to accommodate parking spaces for 30 ADG I based aircraft
- Stormwater management, including the construction of two underground basins to address water quantity management, and two manufactured treatment devices and porous pavement to address water quality management
- Installation of utilities including sanitary sewer, which would require approximately 4,420-SF of ground disturbance

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete