Nashua-Manchester Commuter Rail (Capitol Corridor) Project EA
PROJECT WEBSITE: https://www.nh.gov/dot/projects/nashuamanchester40818/index.htm
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
The New Hampshire Department of Transportation (NHDOT), in coordination with the Massachusetts Bay Transportation Authority (MBTA) and the Massachusetts Department of Transportation (MassDOT), propose to develop a commuter rail extension project from Lowell, MA to Manchester, NH. The Nashua-Manchester Commuter Rail (Capitol Corridor) Project would extend the existing MBTA passenger rail service approximately 30 miles northward from Lowell, MA to Nashua and Manchester, NH using approximately 9 miles of existing MBTA railway and approximately 21 miles of existing Pan Am Railways’ New Hampshire Main Line railway. The project proposes rail corridor infrastructure upgrades along 30 miles of railway, the construction of four new commuter rail stations in South Nashua, Downtown Nashua, Bedford, and Downtown Manchester, and one layover facility Manchester.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|