NORTH COUNTY CORRIDOR: CONSTRUCT EXPRESSWAY ON NEW ALIGNMENT

PROJECT WEBSITE: State Route 108/North County Corridor

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/01/2023

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

California

California

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The California Department of Transportation (Caltrans), in cooperation with the North County Corridor Transportation Expressway Authority (NCCTEA), proposes to construct the North County Corridor New State Route 108 (SR-108) Project. The NCCTEA is represented by Caltrans District 10, Stanislaus County, and the Cities of Oakdale, Riverbank and Modesto. Caltrans is the lead agency for both National Environmental Policy Act (NEPA) and California Environmental Quality Act (CEQA) compliance.

The project lies in northern Stanislaus County between Tully Road SR-219 at the western end, to SR-108/SR-120 at the eastern end. The project area is generally bounded by SR-108/120 on the north, Kiernan Avenue/SR-219/Claribel Road on the south, Tully Road on the west, and Lancaster Road on the east. Within the limits of the project, the current location of SR-108 is a conventional two-lane, undivided highway with two 12-foot-wide lanes, flanked by 2- to 4-foot-wide non-standard shoulders.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete