North Houston Highway (IH 45)
PROJECT WEBSITE: North Houston Highway Improvement Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/31/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
The North Houston Highway Improvement Project is a proposal by the Texas Department of Transportation (TxDOT) to modify the North Freeway (Interstate Highway 45 or IH 45) between the Sam Houston Parkway (Beltway 8) and the Southwest Freeway (US 59/IH 69) in Houston, Texas. The project is divided into three segments:
Segment 1: IH 45 from Beltway 8 to IH 610
Segment 2: IH 45 from IH 610 to IH 10
Segment 3: IH 45 from IH 10 to US 59/IH 69, IH 10 from IH 45 to US 59/IH 69 and
IH69/US 59 from IH 10 to IH 45 The project corridor is 16 miles long.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|