North Houston Highway (IH 45)

PROJECT WEBSITE: North Houston Highway Improvement Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

2 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Other Agencies with Actions or Authorizations:

No icon

States

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

The North Houston Highway Improvement Project is a proposal by the Texas Department of Transportation (TxDOT) to modify the North Freeway (Interstate Highway 45 or IH 45) between the Sam Houston Parkway (Beltway 8) and the Southwest Freeway (US 59/IH 69) in Houston, Texas.  The project is divided into three segments:
 Segment 1: IH 45 from Beltway 8 to IH 610
 Segment 2: IH 45 from IH 610 to IH 10
 Segment 3: IH 45 from IH 10 to US 59/IH 69, IH 10 from IH 45 to US 59/IH 69 and
IH69/US 59 from IH 10 to IH 45 The project corridor is 16 miles long.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete