Oakland Alameda Access Project
PROJECT WEBSITE: https://www.alamedactc.org/programs-projects/highway-improvement/oakland-alamed…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/20/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
California, CalTrans
Description:
The California Department of Transportation (Caltrans), in partnership with the Alameda County Transportation Commission (Alameda CTC), proposes to improve mobility and accessibility, traffic operations, and bicycle and pedestrian facilities through the Oakland Alameda Access Project (proposed project) on State Route 260 (SR-260) (post mile [PM] realignment [R] 0.78 to PM R1.90) and on Interstate 880 (I-880) (PM 30.47 to PM 31.61) in the cities of Oakland and Alameda in Alameda County, California
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|