Ogden/Weber State University Transit Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/22/2019
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
The Ogden/WSU BRT is a 5.3-mile Bus Rapid Transit project in Ogden, UT connecting from the Ogden FrontRunner commuter rail station to Weber State University and McKay Dee Hospital. It will include13 stations and 1.8 miles of exclusive bus lanes from 32nd Street & Harrison up to the Dee Events Center. The project will improve the existing bus service in one of UTA's most successful markets. By enhancing the transit facilities and amenities that connect employment, educational hubs, residential areas, shopping areas, public resources, historic districts,cultural landmarks, and entertainment venues in central Ogden, the project would further improve mobility and accessibility for the people who live, work, and visit the project study area.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|