Pennsylvania and Potomac Avenues SE, Intersection Improvement Project (1306-EA)
PROJECT WEBSITE: Pennsylvania & Potomac Avenues SE Intersection Improvement Study
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/08/2017
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
Department of Transportation, Federal Highway Administration
Description:
This project proposes to enhance safety at the intersections of Pennsylvania and Potomac Avenues SE for neighborhood pedestrians and transit users of the Potomac Avenue Metrorail Station and the numerous area bus stops. The proposed project would remove some of the current conflicting pedestrian crossings and replace them with more direct routes for pedestrians and transit users.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|