Pharr Bridge Expansion

PROJECT WEBSITE: https://www.txdot.gov/projects/hearings-meetings/pharr/2023/pharr-reynosa-10112…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/06/2023

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The proposed facility includes a new tolled bridge with four 12-foot main lanes identical in configuration to the existing bridge. The new bridge would accommodate commercial and non-commercial traffic in both directions of travel. A seven-foot striped shoulder is proposed on the west side of the bridge. 

The new bridge would include standard deck drains and would require a total of approximately 0.98 acres of new right-of-way along the east side of the existing bridge at two separate locations for the foundations of the overhead sign bridges.  Approximately 0.06 acres of the new ROW are owned by property owners along the east side of the existing bridge, and the remaining 0.92 acres are owned by the City of Pharr which is the sponsor of the project

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete