Phoenix Sky Harbor International Airport Sky Train Stage 2
PROJECT WEBSITE: PHX Sky Train Stage 2 EA project site
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/14/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
Department of Transportation, Federal Aviation Administration
Description:
The proposed project involves the following elements: Construct approximately 2.2 miles Sky Train from Terminal 3 to the Rental Car Center; construct a West Ground Transportation Center Sky Train Station (WGTC), including a platform, and a parking garage; construct a platform on the third level of the RCC for Sky Train; construct interim surface roads to accommodate the WGTC Sky Train station and parking facility; construct an electrical substation to power the train; construct a propulsion facility; and expand the Sky Train Maintenance Facility to accommodate additional train cars.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|