Plumas 70 Permanent Restoration
PROJECT WEBSITE: https://dot.ca.gov/caltrans-near-me/district-2/d2-projects/d2-plumas-70-permane…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/24/2020
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects

LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:

California
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The California Department of Transportation (Caltrans), using both state and federal funds, is proposing a permanent restoration project to repair storm-related damage to SR 70 at multiple locations (from post mile 0.00 to 29.9) in Plumas County.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|