Port Authority Bus Terminal Replacement Facility EIS

PROJECT WEBSITE: http://www.pabtreplacement.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/04/2024

0 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

The Port Authority of New York and New Jersey proposes to replace the existing Port Authority Bus Terminal in Manhattan, New York, with a new Main Terminal, Storage and Staging Facility, and associated ramp infrastructure.  The Project includes the construction of two decks over the below-grade portions of Dyer Avenue and the Lincoln Tunnel Expressway, which after construction would be converted to publicly accessible open space.  The project would be accompanied by private development consisting of two tower structures.  The Bus Terminal Replacement Facility, the Deck-Overs, and private development are collectively referred to as the Port Authority Bus Terminal Replacement Facility Project.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete