Programmatic Environmental Impact Statement (PEIS) for Proposed SpaceX Starship-Super Heavy Launch and Landing Operations at the Boca Chica Launch Site at Starbase, Texas and Expansion of Starship Landing and Expenditure Locations

PROJECT WEBSITE: https://www.faa.gov/space/stakeholder_engagement/spacex_starship

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/17/2027

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

The FAA’s Federal action is to modify SpaceX’s vehicle operator license (VOL 23-129) to authorize SpaceX’s proposed action of increasing Starship-Super Heavy operations at the Boca Chica Launch Site at Starbase, TX, expanding Starship landing and expenditure locations, and subsequent license modifications or renewals under 14 CFR Part 400 that are within the scope of this PEIS. The FAA’s Federal Action also includes FAA’s issuance of temporary airspace closures.

SpaceX’s Proposed Action is to expand Starship-Super Heavy launch and Super Heavy and Starship landing operations at the Boca Chica Launch Site at Starbase to support the evolving needs of the Starship program and broader space exploration objectives . The Proposed Action is structured in two phases.

Phase 1 would include up to 100 annual launches and up to 200 annual landings (100 of Starship and 100 of Super Heavy). Launches and landings could occur any day or time of the week.

Phase 2 would include up to 456 launches and 912 annual landings (456 of Starship and 456 of Super Heavy). Launches could occur at any time of day, but would only occur Monday through Friday.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete