Proposed Liloa Drive Extension (Vicinity of East Waipuilani Road to Vicinity of Kaonoulu Street)

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/12/2026

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Highway Administration

Description:

The County of Maui, Department of Public Works proposes a 4,900-foot extension of Liloa Drive from the vicinity of East Waipu‘ilani Road to the vicinity of Ka‘ono‘ulu Street. The proposed roadway improvements will include curb, gutter, sidewalk, curb ramps, bridge crossings at existing drainageways, a shared use path for both pedestrians and bicyclists, signage and striping, utility adjustments and relocations, and landscaping.  While the project will primarily occur within the existing road right-of-way (ROW) that has long been planned for the Liloa Drive Extension project, construction will require temporary rights-of-entry (ROE) or temporary construction easements from some landowners immediately abutting the corridor to facilitate construction of the project. In addition, a limited number of permanent easements and acquisitions will be required.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete