Raritan River Bridge Replacement
PROJECT WEBSITE: Link to Project Website
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/13/2017
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Other Agencies with Actions or Authorizations:
New Jersey
Department of Transportation
Description:
New Jersey Transit is proposing to replace the existing century old, 3,000 foot long Raritan River Swing Bridge damaged by Superstorm Sandy. When constructed, the new rail bridge will be more resilient to coastal flood damage, providing more efficient and reliable commuter rail service on New Jersey Transit’s North Jersey Coast Line. The new bridge will provide a similar ancillary benefit to freight rail operating on the New Jersey Transit track and include a new movable span to improve the safety and reliability of maritime navigation on the Raritan River.
The scope of the project is:
- Construction of a new rail bridge spanning the mouth of the Raritan River between the City of South Amboy and City of Perth Amboy, New Jersey. The new bridge will be located parallel to- and immediately west of- the existing rail bridge.
- Replacement of the existing 300-foot swing bridge moveable span with a 300-foot lift bridge span to improve maritime navigation safety and capacity.
- Removal/demolition of the existing bridge following completion of the new bridge.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|