Red Rock Safety

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/24/2028

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Description:

This section of US 395 was identified in the statewide crossover collision monitoring program for higher-than-average fatal collision rates for the period between January 1, 2017 and December 31, 2021. Of the 33 total crossover and run-off-road collisions identified within this segment, eight resulted in fatalities, seven involved injuries, and 18 were property damage only. The fatal collision rate was 2.2 times greater than the statewide average for similar facilities.

Caltrans proposes pavement widening, and other safety improvements, to 11.5 miles of United States Route 395 (US 395) in Lassen County. The programmable project alternative, Alternative A, will: • Provide a 12-foot paved median with concrete barrier and 8-foot paved shoulders throughout the project limits • Improve the CRZ throughout the project limits • Extend 46 culverts • Widen two bridges: 07-0023 Long Valley Creek and 07-0068 Galeppi UC • Install 950 LF of new guardrail • Construct 10 truck turnouts

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete