USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Riv 10 Blythe Pavement Rehab: mainline, shoulders, ramps (R134.0/R156.5)

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/27/2020

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

California

California

Description:

The California Department of Transportation (Caltrans) District 8 proposes to restore
and extend the life of the existing pavement on U.S. Interstate 10 (I-10) from Caltrans
post mile (PM) 134.00 to 156.50 within the city of Blythe and unincorporated portions
of Riverside County (Project). The Scope of the work includes; removal of existing
mainline AC pavement, removal of existing inside and outside shoulders, removal and
replacement of existing drainage inlets, all dikes, and over-side drains; removal and
replacement of all rumble strips, removal of guardrails and installation of Midwest
Guardrail System (MGS) with vegetation control; mill and overlay of all on and off
ramps with HMA- including those at the Wiley’s Well Rest Area; construction of CRCP
or JPCP and the associated base for traveled-way and all shoulders, including outside
shoulder backing on both roadbeds; widening of existing bridges, regrading of the
median and areas between the shoulders and the Caltrans ROW; construction of a
10-foot lane (cross-over lane) in the inside shoulder for traffic control; restriping,
construct reinforced concrete slope paving on all structures; and upgrading of the
existing ADA facilities at ramp termini.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete