RIV 215 ETHANAC ROAD INTERCHANGE IMPROVEMENTS
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/19/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The project addresses the following needs and transportation deficiencies: due to continued increases in traffic volumes associated with planned development and corridor improvements in the area, this interchange is not expected to satisfy operational performance standards by the design horizon year of 2055; existing geometric deficiencies such as no ramp metering, lack of maintenance vehicle pullouts, and lack of proper deceleration and acceleration lane lengths; and existing gaps in the pedestrian and bicycle infrastructure across the interchange break the multi-modal connection between communities and businesses on either side of I-215. As identified in the 2022 City of Perris General Plan, buffered bike lanes (class II) are recommended along Ethanac Road. Revised June 2020 Page 2 of 18 Without the project, the operation of the interchange is expected to deteriorate, resulting in increased congestion, delays, and substandard transit and emergency service response times.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|