RM 150
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
The Texas Department of Transportation (TxDOT) is proposing a new location realignment of RM 150 from to the existing RM 150 west of Kyle. The proposed project length is approximately six miles. The existing RM 150 is a two-lane roadway. The proposed realignment would be a four-lane, divided highway.
At this time, 12 alternatives (Alternatives 1 through 12) are proposed as possible routes for the new location roadway. The proposed new location roadway of RM 150 would bypass Kyle from RM 150 west of Kyle and connect to I-35 south of Kyle at Yarrington Road (County Road [CO] 159.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|