USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Route 68 Corridor Operational Improvments

PROJECT WEBSITE: SR 68 Scenic Highway Plan

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/30/2025

1 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Other Agencies with Actions or Authorizations:

California

California

Description:

The California Department of Transportation (Caltrans) proposes the following project that would provide build alternatives which would either covert nine intersections into roundabouts OR add adaptive signal control with some intersection improvements.  Each alternative also includes wildlife crossing improvements to existing culverts and/or installation of directional fencing to deter wildlife from entering SR 68 at eight locations.

The project will include the following intersections: SR 68/Josselyn Canyon Road (post mile 5.2); SR 68/Olmsted Road (post mile 5.6); SR 68/SR218 Canyon del Rey Boulevard (post mile 6.8); SR68/Ragsdale Drive (post mile 7.0) SR 68/York Road (post mile 8.2); SR 68/Pasadera Drive (post mile 9.8); SR 68/Laureles Grade (post mile 11.2); SR 68/Corral de Tierra Road (post mile 12.9); SR 68/San Benancio Road (post mile 13.3).

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete