San Bernardino Co. I-15 Replace Rock Slope Protection - Six Bridge Locations

PROJECT WEBSITE: Caltrans District 8 Current Projects

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/01/2024

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Caltrans

LEAD AGENCY
California, CalTrans

Description:

Reconstruct the existing Rock Slope Protection (RSP) underneath six bridges at Mescal Ditch RT (Br. No. 54-0303R, PM 166.8), Mescal Ditch LT (Br. No. 54-0303L, PM 166.8), Ivanpah Ditch RT (Br. No. 54-0316R, PM179.4), Ivanpah Ditch LT (Br. No. 54-0316L, PM 179.4), Cenda Ditch (Br. No. 54-1308L, PM 172.1L) and Telephone Wash (Br. No. 54-0233L, R110.4) to mitigate the scour critical issues and/or as identified in the PIP. The project also includes upgrading Metal Beam
Guardrail (MBGR) to Midwest Guardrail System (MGS). The purpose of this project is to preserve the structural integrity of these bridges in a safe and economic
manner.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete