San Joaquin River (Garwood) Bridge Rehab
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CLASS OF ACTION CHANGED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
The Garwood Bridge over the San Joaquin River (Bridge No. 29-0050) is a steel through-truss swing span and reinforced concrete deck on steel stringers and floor beams resting on reinforced concrete piers set on timber piles. In the past, the bridge used to open for vessel traffic but has been closed since 1984.
The project is located on State Route 4 at post-mile (PM) 14.2. There are three proposed build alternatives, and a no-build alternative. The no-build alternative would not meet the purpose and need identified for this project. The three build alternatives are proposed as follows:
1. Structural rehabilitation: Rehabilitating the bridge deck, repairing the damaged steel truss members, restoring and repairing fracture-critical beams, and upgrading the bridge rails to current standards.
2. Structural and mechanical rehabilitation: Rehabilitating the bridge deck, repairing the damaged steel truss members, repairing fracture-critical beams, restoring the mechanical and electrical components for an emergency bridge opening, and upgrading the bridge rails to current standards.
3. Bridge replacement: Demolition/removal of the existing bridge and construction of a replacement with an approximate 9 foot high profile at the bridge, capable of allowing vessel passage requirements per Coast Guard regulations, without the use of any mechanical opening device. Installation of the new bridge will also require removal of the smaller Cordes Ranch UC (Bridge No. 29-0051), approximately 26 meters east of Garwood Bridge.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|