SCR State Route 1 Auxiliary Lanes
PROJECT WEBSITE: https://sccrtc.org/projects/streets-highways/hwy1corridor/bayporter-statepark/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/10/2021
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Description:
The California Department of Transportation (Caltrans) proposes to construct northbound and southbound auxiliary lanes between Bay Avenue/Porter Street and State Park Drive interchanges on SR 1 in Santa Cruz County and the City of Capitola. In addition, shoulders at the offramps would be widened in order to accommodate bus-on-shoulder within the interchanges and construct a bicycle/pedestrian overcrossing at Mar Vista.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|