Second Avenue Subway: Phase 2
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
11/15/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
Following the recent opening of Phase 1 of the Second Avenue Subway (SAS) in Manhattan, the Metropolitan Transportation Authority (MTA) is now proposing to advance SAS Phase 2, the portion of the new subway that extends service between 96th Street and 125th Street. Phase 2 work would consist of a number of components including subway tunnels; three new stations - at 106th St., 116th St., and 125th St.; track work; traction power substations; circuit breaker houses; facility electrical power; fan plants; ventilation systems; pump rooms; signal and communications work; entrances, and ancillary facilities to support operation of the stations. The MTA is advancing SAS to be constructed in four phases; which, at full length, will stretch 8.5 miles along Manhattan’s East Side, from 125th St.in Harlem to Hanover Square in Lower Manhattan
The Supplemental Environmental Assessment to the Second Avenue Subway Final Environmental Impact Statement: Phase 2 (Supplemental EA) was prepared in accordance with the National Environmental Policy Act (NEPA) for the Federal Transit Administration (FTA) as lead agency to evaluate potential impacts related to the advancing design of Phase 2. A Final Environmental Impact Statement (FEIS) and Record of Decision (ROD) were issued in 2004 for the full-length Project to evaluate its impacts as required by NEPA.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|