Seldovia Bay Ferry Dock Refurbishment Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Class of Action Changed

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CLASS OF ACTION CHANGED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

The Seldovia Bay Ferry Dock Refurbishment Project proposed by Seldovia Village Tribe would relocate the existing floating ferry dock in the City of Seldovia, Alaska approximately 40 feet closer to the shoreline, and rotate it approximately 90 degrees. This reconfiguration would lessen the impact of northerly wave swells on the structure. The existing dock is not safe or functional for vessels or pedestrians. Since the construction of the existing dock approximately ten years ago, the piles are no longer secure and shift during wave swells. The purpose of the Project is to refurbish the existing dock to bring it into a usable, safe, and sustainable condition. Alternatives considered include a No Build and a Build Alternative.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete