SH 105
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/20/2020
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
Texas
Description:
The proposed project would widen the existing SH 105, from 10th Street in Conroe, Texas to Business 15 in Cleveland,
Texas and would provide sidewalks along both sides of the roadway for the entire length of the project.
The proposed project would reconstruct and widen the existing two-lane undivided facility to a four-lane facility with a
continuous two-way turn lane. SH 105, from 10th Street in Conroe to Business 105 near Cleveland, would be reconstructed
and widened to the north and south. The proposed project would provide sidewalks and bicycle accommodations along
the north and south sides of SH 105 for the entire length of the proposed project. The proposed project includes a curb
and gutter system along approximately 75 percent of the proposed project with open ditches along the remaining
easternmost length of the proposed project.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|