SH 105

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/20/2020

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation

SECTOR
Surface Transportation

Project Category

CATEGORY
Project Category DOT Projects

Texas

LEAD AGENCY
Texas

Description:

The proposed project would widen the existing SH 105, from 10th Street in Conroe, Texas to Business 15 in Cleveland,
Texas and would provide sidewalks along both sides of the roadway for the entire length of the project.
The proposed project would reconstruct and widen the existing two-lane undivided facility to a four-lane facility with a
continuous two-way turn lane. SH 105, from 10th Street in Conroe to Business 105 near Cleveland, would be reconstructed
and widened to the north and south. The proposed project would provide sidewalks and bicycle accommodations along
the north and south sides of SH 105 for the entire length of the proposed project. The proposed project includes a curb
and gutter system along approximately 75 percent of the proposed project with open ditches along the remaining
easternmost length of the proposed project.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete