SJ 4 CAPM
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/04/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
The California Department of Transportation (Caltrans) proposes to dig out and repair localized areas of severe pavement failure and place a Rubberized Hot Mix Asphalt (RHMA) overlay on the roadway surface throughout the project limits. The project limits are on SR 4 from Golden Gate Avenue Overcrossing at SR 99 in the City of Stockton in San Joaquin County to 0.5 mile east of Dunton Road in Town of Telegraph in Stanislaus County.
The scope of work also includes rehabilitating 23 culverts at various locations, removing and replacing bridge rails at Duck Creek Bridge (# 29-0053) in San Joaquin location, upgrading and/or installing warning signs, removing and upgrading existing guardrails and dikes at locations warranted, construct new sidewalks and upgrading existing sidewalks and curb ramps in compliance with the Americans with Disabilities Act (ADA), and placing shoulder backing and rumble strips.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|