SJ-5-REPLACE PARADISE CUT BRIDGE
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/04/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
California Department of Transportation (Caltrans) proposes to replace the bridge at Paradise Cut in San Joaquin County. The proposed project would require full bridge replacement and construction of a work trestle on each side of the bridge. A construction easement of 80 feet will be needed throughout the
course of construction spanning two to three construction seasons between June 1 and October 15 each year. When completed, the new structure would be about 10 feet wider and 18 feet longer than the existing bridge. Construction would be staged; traffic could move on half the bridge deck as the rest is rebuilt. The new structure would be on piers supported by 36-inch-diameter driven piles.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|