SOL-113-Asphalt Pavement Roadway Rehabilitation
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/01/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
Project Category
DOT Projects
LEAD AGENCY
California, CalTrans
Description:
This project is a roadway resurfacing, restoration, and rehabilitation (3R) project on State Route (SR) 113 in Solano County, from one mile south of Old Alamo Creek Bridge (PM 8.5) to W. Chestnut Street (PM 19.0), in Dixon, California. The scope of work includes reconstructing the roadway structural section, widening to a standard 40-foot paved width, providing Class II bike lanes, realigning roadway, replacing culverts, bridge widening and/or replacement (3 bridges), providing permanent treatment best management practices (BMPs), sidewalk gap closures, curb ramp upgrades, and acquiring additional right of way to accommodate the proposed improvements.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|